Before paying a deposit, confirm the commercial scope, approved product revision, sample status, accessory and packaging contents, quality and inspection requirements, payment milestones, change-control rules, and the conditions that authorize production. The goal is to ensure that the buyer and supplier are funding the same order.
This inflatable SUP order checklist is for brand owners and purchasing managers who have completed initial development discussions and are preparing a purchase order. It does not replace a contract, legal review, destination-market compliance assessment, or customs advice.
1. Confirm the Full Quotation Scope
The quotation, purchase order, and pro forma invoice should identify the same product, quantity, currency, trade term, and included services. Review the price line by line instead of relying on the total.
Confirm:
- Board model or custom project reference
- Included accessories, quantities, specifications, and packaging
- Artwork, printing, material, component, or tooling charges
- Sample, testing, inspection, documentation, and logistics items
- Items expressly excluded from the quotation
A lower quotation may exclude retail packaging, inspection support, or product changes included elsewhere. The ALS service workflow shows the broad path from quotation and order confirmation to production, but every order still needs its own written scope.
2. Identify the Exact Product Revision
A model name or reference photo is not enough for a customized board. Confirm the latest approved specification, drawing, artwork, color references, component list, accessory list, and packaging revision. Use clear file names or revision dates so an outdated attachment cannot become the production instruction.
Confirm:
- Project or model code, dimensions, and construction
- Valve, fin system, D-rings, handles, deck pad, and other fittings
- Artwork file, placement, color references, and print method
- Accessory and packaging revision
List unresolved specifications as open issues. Paying a deposit should not be interpreted as approval of technical details that remain open.
3. Separate Sample Approval from Production Release
Record what the approved sample proves, any accepted deviations, and which documents control details that one sample cannot demonstrate.
If the final sample is not approved, state whether the deposit authorizes:
- Continued sampling
- Material reservation
- Full production
These are different commitments.

Mass production should begin only after the named release conditions are met and an authorized buyer representative gives written approval.
4. Lock the Accessory, Packaging, and Labeling Scope
Confirm a pack-out list for each sellable unit and master carton. Identify standard accessories, project-specific items, retail packaging, manuals, warning labels, barcodes, carton marks, and any agreed spare components.
Destination-market wording should be reviewed by the buyer’s qualified compliance resources. Generic supplier labels are not automatically suitable for every market.
5. Define Quality Evidence and Inspection Responsibility
“Good quality” is not an acceptance requirement. Identify the documents and observations used to judge the order:
- Specification and appearance checkpoints
- Required records
- Inspection method, where applicable
- Inspection responsibility
- Report timing
- Process for closing nonconforming findings
The ALS quality assurance overview describes available control areas. Buyers should still confirm which checks apply to the exact model and order.
If ALS pages or previous documents show inconsistent test durations or conditions, use only the project-specific requirement confirmed in writing.
6. Confirm Schedule Dependencies
Define when lead time begins:
- Deposit receipt
- Artwork approval
- Specification freeze
- Sample release
- Material confirmation
Record expected milestones for material confirmation, production, inspection, corrective action, packing, and shipment booking.
Keep dates conditional while approvals, custom materials, testing, or logistics remain open. A useful schedule states its dependencies instead of presenting an unsupported delivery guarantee.
7. Match Payment Milestones to Deliverables
Confirm the amount, currency, payment method, beneficiary, invoice reference, and deliverable attached to each payment.
Verify bank details through an established contact, especially after any change in beneficiary or account information.
The commercial documents should also address:
- Post-payment specification changes
- Custom materials already purchased
- Delays caused by outstanding buyer approvals
This is commercial risk allocation, not legal advice.
8. Define Change Control
Require written change requests that identify:
- The new revision
- Reason for the change
- Price effect
- Schedule effect
- Sample or retesting requirement
- Authorized approvers
Once approved, the new revision must replace the old one in the order file. Two competing specifications must not remain active.
9. Confirm Shipping Scope and Documents
Confirm the trade term and named place, then allocate responsibility for:
- Export formalities
- Freight booking
- Insurance, where applicable
- Destination clearance
- Taxes
- Delivery appointments
- Final-mile handling
Ask a freight forwarder or customs adviser to verify destination requirements.
List the commercial and shipping documents expected for the specific transaction rather than relying on a generic document package.
Pre-Deposit Release Decision
- Release: Scope, product revision, approvals, quality requirements, payment details, and production conditions are confirmed.
- Conditional release: Funds may reserve materials or continue development, but production waits for named approvals.
- Hold: Product identity, quotation scope, beneficiary details, or the acceptance basis remains unclear.
One-Page Confirmation Record
Keep the following information in one controlled order file:
- Supplier and buyer legal names
- Quotation and invoice references
- Product and packaging revisions
- Sample status
- Production-release condition
- Accessory list
- Quality references
- Payment milestone
- Verified beneficiary
- Open issues, owners, and due dates
- Authorized approvers
Frequently Asked Questions
Can a buyer pay before the final sample is approved?
Sometimes, but the authorization must be explicit. The deposit may cover sampling or material reservation without releasing mass production. State the permitted activity and remaining approval conditions in writing.
Is a pro forma invoice enough to start production?
Not by itself. It may record commercial terms, but the order also needs an identifiable product revision, approval status, included components, acceptance basis, and production-release condition.
What if the supplier changes bank details?
Pause payment and verify the change through a trusted contact using an independent communication channel. Do not rely only on the email announcing the change.
Request a Pre-Deposit Specification Review
Before releasing funds, consolidate the quotation, final specification, accessory list, packaging files, approval status, quality requirements, and open issues into one review package.
ALS can review the package against the intended SUP project and identify mismatched revisions or missing production-release information.